Stage 1:

  • Earthworks are progressing on-site, with final water installation to occur towards the beginning of April.

Titles Update:

  • Stage 1 titles are forecast to be issued late June 2022.

Stage 2:

  • Sewer installation is currently underway, with drainage pit and pipe also now underway.

Titles Update:

  • Stage 2 titles are forecast to be issued Q3 2022.

Stage 2:

  • Earthworks have commenced and are due for completion in April 2022.

Titles Update:

  • Stage 3 titles are forecast to be issued Q2/Q3 2022.

Stage 3:

  • Earthworks have commenced, with sewer installation currently underway.

Titles Update:

  • Stage 3 titles are forecast to be issued Q3 2022.