Stage 11


As works continue to progress, we are happy to provide an update from the construction team onsite.

Titles are forecast for Q2 2025*.

March 2025:

  • Construction completed and working through compliance.

February 2025:

  • Construction completed and working through compliance.

January 2025:

  • Footpath works are nearing completion.
  • Topsoil works are almost complete.

December 2024:

  • Electrical and communication cable works are now complete.
  • Footpath works are now underway
  • Base course asphalt is now complete.

November 2024:

  • Service trenching is now complete.
  • Electrical reticulation works to commence shortly.

October 2024:

  • Water works and kerbs are now complete.
  • Road base works are now underway.

September 2024:

  • Sewer works and drainage works are now complete.
  • Water works to commence shortly.

August 2024:

  • Sewer works are underway with drainage works to commence shortly.

July 2024:

  • Bulk earthworks are complete.
  • Sewer reticulation works to commence shortly.