As works continue to progress, we are happy to provide an update from the construction team onsite.
Titles are forecast for January – March 2025*.
November 2024:
- Electrical and communication cable works are now complete.
- Footpath works are now underway
- Base course asphalt is now complete.
November 2024:
- Service trenching is now complete.
- Electrical reticulation works to commence shortly.
October 2024:
- Water works and kerbs are now complete.
- Road base works are now underway.
September 2024:
- Sewer works and drainage works are now complete.
- Water works to commence shortly.
August 2024:
- Sewer works are underway with drainage works to commence shortly.
July 2024:
- Bulk earthworks are complete.
- Sewer reticulation works to commence shortly.