Stage 12


As works continue to progress, we are happy to provide an update from the construction team onsite.

Titles are forecast for January – March 2025*.

December 2024:

  • Electrical and communication cable works are now complete.
  • Footpath works are now underway.
  • Base course asphalt is now complete.

November 2024:

  • Service trenching is now underway.

October 2024:

  • Water works and kerbs are now complete.
  • Road base works are now underway.

September 2024:

  • Sewer and drainage works are now complete.
  • Water works to commence shortly.

August 2024:

  • Sewer works are underway with drainage works to commence shortly.

July 2024:

  • Bulk earthworks are underway.