As works continue to progress, we are happy to provide an update from the construction team onsite.

Titles are forecast for January – February 2025*.

November 2024:

  • Topsoil works are continuing.
  • Road signage and line marking installation is underway.

October 2024:

  • Concrete works such as driveways and kerbs are complete.
  • Topsoil works are underway.

September 2024:

  • All drainage works for the stage are complete.
  • Kerb are works underway.

August 2024:

  • Sewer and gas reticulation works are complete.
  • Drainage and electrical conduits are being installed; following this, kerb will be installed.

July 2024:

  • Bulk earthworks are now complete.
  • Drainage works are now underway.