As works continue to progress, we are happy to provide an update from the construction team onsite.
Titles are forecast for February 2025*.
February 2025:
- Plan of Subdivision submitted to the Titles office, pending registration. Titles anticipated in the coming week.
January 2025:
- Construction has now been completed, with Titles forecast for February 2025.
December 2024:
- Finalising the final layer of road.
- Construction is expected to be completed this month.
November 2024:
- Topsoil works are continuing.
- Road signage and line marking installation is underway.
October 2024:
- Concrete works such as driveways and kerbs are complete.
- Topsoil works are underway.
September 2024:
- All drainage works for the stage are complete.
- Kerb are works underway.
August 2024:
- Sewer and gas reticulation works are complete.
- Drainage and electrical conduits are being installed; following this, kerb will be installed.
July 2024:
- Bulk earthworks are now complete.